For enhancing the study environment, building works will be carried out in Library according to the schedule below:
Location | Work Description | Work Period | Arrangement |
4/F Room L404 & 5/F Room L505 |
Renovation | 8 Jun – 15 Sep |
|
3/F Multimedia Commons | Lighting replacement works | 28 Jul – 2 Sep |
|
Front Staircase 1/F – P/F |
Rubber flooring rectification | 1 – 18 Aug |
|
G/F Collaboration Zone 1 (L019 ) | Rain water pipework rectification | 1 – 25 Aug |
|
4/F front staircase and 5/F back staircase | Duct work for new air-conditioning system | 1 – 19 Aug |
|
4/F back staircase and 5/F front staircase | Duct work for new air-conditioning system | 13 – 24 Aug |
|
Library will try shortening the noisy work duration and minimize the disturbance. Sorry for any inconvenience caused. Thank you for your forbearance.