For enhancing the study environment, the building and moving works will be carried out according to the schedule below:
Location | Work Description | Work Period | Arrangement |
---|---|---|---|
L115 | Anti-theft installation | 10 May |
|
L501 | Moving works | 10 May - 30 Jun |
|
Water leakage rectification | 10 May – 30 Jun |
|
|
L505 | Water leakage rectification | 19 May – 30 Jun |
|
L114 & L019 | Power outlet Installation | 16 May – 31 Jul |
|
L019 | Water leakage rectification | 17 Jul – 30 Aug |
|
If you need assistance in obtaining the books in Room L114 and L501, please contact P/F Loan & Return Counter. Noise is unavoidable from these installation and rectification work. We will try to shorten the noisy work duration and minimize the disturbance. Sorry for any inconvenience caused.